Hanghai New Energy Development Co., Ltd. 200MW PV Desertification Control Project

Project Introduction

200,000KW PV Desertification Control Project of HangTai New Energy Development Co., Ltd. in Liangzhou District, Wuwei. It is located in the PV Desertification Control Demonstration Park in Jiuduntan, Liangzhou District, Wuwei, Gansu Province at the edge of the Tengri Desert. The lined-up PV power generation matrix extends all the way, resembling blue “armors”on the vast desert. Zhengtai is building another large-scale PV project to control desertification in Liangzhou, as part of their Blue Sea Plan. The construction of power plant started in August 2022 and up to now 85% had been completed within the PV site. It is scheduled to be connected to the grid with full capacity by June 30, 2023.

Project Overview

Project Type:Centralized

Project Location:Wuwei City, Gansu Province

Project Capacity:240MW

Products Used:182 Bifacial 545/550